Proposal APERTURES.  PART      B        Priority6.1.3.1.1.2    -  FP6-2005-TREN-4                                                  p 48 of 49
           Workpackage number       7     Start /close date / starting event:              0   to  35
           Workpackage title        Project Promotion –Exploitation–Management- IPR
           Participant identity     CIRT                                                   TOTAL
           Person-months            18                                                     18
           Objectives:
              ·   Promote the project and its results
              ·   Prepare the Technology Implementation Plan so as to exploit the results to generate future international joint-
                  venture& project spin-offs
              ·   Ensure smooth and tight drive for the project management targets to achieve success
           Description of work :  6 Mains tasks
           Task 7.1 Project Promotion:
              ·   Dedicated project website with open and restricted access to the project activity results
           Task 7.2Dissemination: (subject to not conflicting with knowledge protection  policies)
              ·   In collaboration with WP6, set-up of a website delivering access to the project on-line management for partners, the
                  Commission  (secured) and the general public
           Task 7.3Exploitation  & post project sustainable activity plans
              ·   Partnership building with SMEs willing to develop the use of the project technology
              ·   Develop relationships with detected B to B markets to profile the Consumer affordability concept.
              ·   Prepare the Technology Implementation Plan
              ·   Assistant to potential to university spin-off
              ·   Design of the surveys (on-line & off line)
              ·   Market assessment
              ·   Post-project sustainable activities plan
           Task 7.4  Online /Off line Project  Management
              ·   Design of coordination system -Design of the internal communication policy
              ·   Design of the Project management system (WBS,WBD, reporting ) with
              ·   Reviews and meeting preparation –
              ·   Design of corrective actions
              ·   Partner's reporting acquisition and consolidation
              ·   Relationship with the EU Commission and reporting
              ·   Steering committee management
              ·   Financial, accounting, and reporting –
              ·   Planning monitoring and updating
              ·   Coordination of Dissemination activities  with other WP involved
           Task 7.5  IPR management
              ·   Co
           Task 7.6  Consortium management :
              ·   Co-ordination of the project activities in particular the overall legal,   contractual, ethical, financial and
                  administrative management
              ·   Preparing, updating and managing the consortium agreement. Overseeing the promotion of gender equality in the
                  project and the ethical issues .
              ·   Overseeing science and society issues, related to the research activities conducted within the   project.
              ·   Obtaining audit certificates by each of the participants
           Deliverables
           D7.1  Project Website for the public at large , surveys
           D7.2.  Website for on-line management and
           D7.3  Market Assessment report and Exploitation plans
           D7.4  Regular progress reports and financial reports, as stated in the contract
           D7.5   Project assessment report at completion + project management platform
           Milestones and expected result
                 M7.0  Contract
                M7 18 Midterm review as a major milestone for the assessment of the project and its continuation
                Result :  An efficient project management