Proposal APERTURES.  PART      B        Priority6.1.3.1.1.2    -  FP6-2005-TREN-4                                                  p 46 of 49


          Workpackage number     5B       Start /close date / starting event:    23    to  35        (12 months)
          Workpackage Title      Real-Scale  Plug-Play Green Grid System Implantation & Tests ON MARIBOR SITE
          Participant identity    TCPE      MARI    CIRT     SASS                                 TOTAL
          Person-months          22        10       2       2                                     36
          Objectives:
          Reminder: The WP1 stated that theMaribor site RES assessment had somehow  been done in the past; This work package
          will start with an new assessment as conducted in WP1 for Favignana Islanded site.
          The  experience  gained  with  WP1  will  be  transferred  to  the  Maribor  site  and  the  updated  evaluation  tools  too.
          A specific global report equivalent to the WP1 deliverables will be produced.

          Starting from the objectives of WP1, WP2, WP3, WP4, the main objective of the workpackage is verification of the proposed
          RES generation system inside the electrical grid of Maribor. This verification will be done at two levels:
             3.  Experimental photovoltaic plant will be connected to the electrical grid of Maribor. In the PVP the correct behaviour
                 of the MSC will be tested in terms of generated power, optimal exploitment of the RES in input, power quality and
                 EMC issues.
             4.  Measurements  of  electrical  energy  quality  will  be  done  in  terms  of  higher  harmonics,  EMC,  flicker  etc.
                 Compatibility of the PVP with new MSC device will be tested and different steps will be done for improvement. The
                 electrical grid of Maribor, with the different MSC connected in the MV grid with automatic reconnection ability,
                 will  be  tested  at  a  system  level  in  terms  of  optimal  dispatching  of  electric  energy  and  the  variation  of  load,
                 management of energy flows inside the grid in normal and faulty conditions. With this regard the goodness of the
                 telecontrol system which coordinates the behaviour of the system will be verified.
          Description of work :
          The work will be organized following the two objectives above.
                                 th
                           th
          TASK 5.1 / From 24  to 28  month various MSCs will be installed in photovoltaic plant in Maribor and connected with
          electrical  grid  in  output  and  the  photovoltaic  plant  in  input.  At  the  same  time  the  supervisory  control  system  and  its
          telecontrol will be installed and tested.
                            th       th
          TASK 5.2 From the 29  to the 32  month the grid will be tested during normal working conditions, verifying :
             ·   for the MSC the generated power, the optimal exploitation of the RES in input, and power quality and EMC issues
             ·   for the electrical grid, the optimal dispatch of electric energy according to the variation of load and the management
                 of energy flows.
                         rd
                              th
          Task 5.3 :From 33  to 36  month, the grid will be tested in critical working conditions, like high nonlinear loads producing
          high  levels  of  harmonics,  highly  reactive  loads  and  faulty  conditions.  As  a  last  point,  the  production  of  energy  will  be
          measured and verified.  The reduction of CO 2  will be calculated.
          Deliverables
          ·  D5B.1 Testing of the MSC connected to the electrical grid of Maribor;
          ·  D5B.2 Testing of the supervisory control system of the grid and its telecontrol system;
          ·  D5B.3 Testing of the electrical grid of Maribor with MSCs and supervisory control in normal working conditions;
          ·  D5B.4 Testing of the electrical grid of Maribor with MSCs and supervisory control in critical working conditions;
          ·  D5B.5  Evaluation of the reduction of CO 2  emissions thanks to the RES in Maribor;

          Milestones and expected result
                               th
          ·  M 5.1 Meeting at the 24  month with all partners to prepare installation of equiments;
                           th
          ·  M 5.2 Metting at 28  month to verify the correct installation of all MSCs in the grid and the telecontrol system;
                            th
          ·  M 5.3 Meeting at 32  month to verify the correct working of system (PVP) with its MSC and the grid with the supervisory
           control in normal working conditions;
                            th
          ·  M 5.4 Meeting at 32  month to verify the correct working of grid with its MSC and the grid with the supervisory control in
           critical working conditions;
          ·  R 5.1 Maribor population satisfaction ;
          ·  R 5.2 Green on grid implementation;
          ·  R 5.3 Report proving the feasibility and the reliability of the proposed technology and pratical solution.