Proposal APERTURES. PART B Priority6.1.3.1.1.2 - FP6-2005-TREN-4 p 45 of 49
Workpackage number 5 Start /close date / starting event: 23 to 35 (12 months)
Workpackage Title Real-Scale Plug-Play Green Grid System Implantation & Tests ON FAVIGNANA SITE
Participant identity CIRTEM UTBM ISSIA SEA SASSO TOTAL
Person-months 6 20 12 5 5 48
Objectives:
Starting from the objectives of WP1, WP2, WP3, WP4, the main objective of the workpackage is verification of the proposed
RES generation system inside the electrical grid of Favignana. This verification will be done at two levels:
1. In each microgrid of those identified inside the electrical grid of Favignana in WP1, in the PCC will be tested the
correct behaviour of the MSC in terms of generated power, optimal exploitment of the RES in input, power quality and
EMC issues.
2. The whole electrical grid of Favignana, with the different MSCs connected in the different microgrids, will be tested at
a system level in terms of optimal dispatching of electric energy from both diesel generators and RES according to the
variation of load, management of energy flows inside the grid in normal and faulty conditions. With this regard the
goodness of the telecontrol system which coordinates the behaviour of all generators (diesel and RES) will be verified.
Description of work :
The work will be organized following the two objectives above.
th th
TASK 5.1 / From 24 to 28 month various MSCs will be installed in each microgrid of Favignana and connected with PCC in
output and the available RES (already installed and tested) in input. At the same time the supervisory control system and its
telecontrol will be installed and tested.
th
th
TASK 5.2 From the 29 to the 32 month the whole grid will be tested during normal working conditions, veryfing :
· for the MSC the generated power, the optimal exploitment of the RES in input, and power quality and EMC issues
· for the whole electrical grid, the optimal dispatch of electric energy according to the variation of load and the
management of energy flows.
rd th
Task 5.3 :From 33 to 36 month, the whole grid will be tested in critical working conditions, like high nonlinear loads
producing high levels of harmonics, highly reactive loads and faulty conditions. As a last point, the save of gasoline not
employed by diesel generators thanks to the RES and the reduction of CO 2 emissions will be verified.
Deliverables
· D5.1 Testing of the MSC connected to the electrical grid of Favignana;
· D5.2 Testing of the supervisory control system of the whole grid and its telecontrol system;
· D5.3 Testing of the whole electrical grid of Favignana with MSCs and supervisory control in normal working conditions;
· D5.4 Testing of the whole electrical grid of Favignana with MSCs and supervisory control in critical working conditions;
· D5.5 Evaluation of the save of gasoline not emplyed by diesel generators thanks to the RES in Favignana;
· D5.6 Evaluation of the reduction of CO 2 emissions thanks to the RES in Favignana;
Milestones and expected result
th
· M 5.1 Meeting at the 24 month with all partners to prepare installation of equiments;
th
· M 5.2 Metting at 28 month to verify the correct installation of all MSCs in the microgrids and the telecontrol system;
th
· M 5.3 Meeting at 32 month to verify the correct working of each microgrid with its MSC and the whole grid with the
supervisory control in normal working conditions;
th
· M 5.4 Meeting at 32 month to verify the correct working of each microgrid with its MSC and the whole grid with the
supervisory control in critical working conditions;
· R 5.1 Favignana population satisfaction ;
· R 5.2 Green on grid implementation;
· R 5.3 Report proving the feasibility and the reliability of the proposed technology and pratical solution.