Proposal APERTURES.  PART      B        Priority6.1.3.1.1.2    -  FP6-2005-TREN-4                                                  p 45 of 49


          Workpackage number     5        Start /close date / starting event:    23    to  35          (12 months)
          Workpackage Title      Real-Scale  Plug-Play Green Grid System Implantation & Tests ON FAVIGNANA SITE
          Participant identity   CIRTEM  UTBM       ISSIA    SEA     SASSO                         TOTAL
          Person-months          6         20       12      5       5                              48
          Objectives:
          Starting from the objectives of WP1, WP2, WP3, WP4, the main objective of the workpackage is verification of the proposed
          RES generation system inside the electrical grid of Favignana. This verification will be done at two levels:
             1.  In each microgrid of those identified inside the electrical grid of Favignana in WP1, in the PCC will be tested the
                 correct behaviour of the MSC in terms of generated power, optimal exploitment of the RES in input, power quality and
                 EMC issues.
             2.  The whole electrical grid of Favignana, with the different MSCs connected in the different microgrids, will be tested at
                 a system level in terms of optimal dispatching of electric energy from both diesel generators and RES according to the
                 variation of load, management of energy flows inside the grid in normal and faulty conditions. With this regard the
                 goodness of the telecontrol system which coordinates the behaviour of all generators (diesel and RES) will be verified.
          Description of work :
          The work will be organized following the two objectives above.
                          th    th
          TASK 5.1 / From 24  to 28  month various MSCs will be installed in each microgrid of Favignana and connected with PCC in
          output and the available RES (already installed and tested) in input. At the same time the supervisory control system and its
          telecontrol will be installed and tested.
                                     th
                            th
          TASK 5.2 From the 29  to the 32  month the whole grid will be tested during normal working conditions, veryfing :
             ·   for the MSC the generated power, the optimal exploitment of the RES in input, and power quality and EMC issues
             ·   for  the  whole  electrical  grid,  the  optimal  dispatch  of  electric  energy  according  to  the  variation  of  load  and  the
                 management of energy flows.
                          rd    th
          Task  5.3  :From  33   to  36   month,  the  whole  grid  will  be  tested  in  critical  working  conditions,  like  high  nonlinear  loads
          producing  high  levels  of  harmonics,  highly  reactive  loads  and  faulty  conditions.  As  a  last  point,  the  save  of  gasoline  not
          employed by diesel generators thanks to the RES and the reduction of CO 2  emissions will be verified.
          Deliverables
          ·  D5.1 Testing of the MSC connected to the electrical grid of Favignana;
          ·  D5.2 Testing of the supervisory control system of the whole grid and its telecontrol system;
          ·  D5.3 Testing of the whole electrical grid of Favignana with MSCs and supervisory control in normal working conditions;
          ·  D5.4 Testing of the whole electrical grid of Favignana with MSCs and supervisory control in critical working conditions;
          ·  D5.5 Evaluation of the save of gasoline not emplyed by diesel generators thanks to the RES in Favignana;
          ·  D5.6 Evaluation of the reduction of CO 2  emissions thanks to the RES in Favignana;
          Milestones and expected result
                               th
          ·  M 5.1 Meeting at the 24  month with all partners to prepare installation of equiments;
                           th
          ·  M 5.2 Metting at 28  month to verify the correct installation of all MSCs in the microgrids and the telecontrol system;
                             th
          ·  M 5.3 Meeting at 32  month to verify the correct working of each microgrid with its MSC and the  whole grid with the
           supervisory control in normal working conditions;
                             th
          ·  M 5.4 Meeting at 32  month to verify the correct working of each microgrid with its MSC and the  whole grid with the
           supervisory control in critical working conditions;
          ·  R 5.1 Favignana population satisfaction ;
          ·  R 5.2 Green on grid implementation;
          ·  R 5.3 Report proving the feasibility and the reliability of the proposed technology and pratical solution.