               reasonable  diameter  coherent  with  the  aforementioned  pressure  drops  was  preliminarily
               calculated, so as to position the corresponding point (identified in the labels) on the graph.


































               Figure 11. Distribution costs in the scenario of connection costs covered by the private customers

































               Figure 12. Distribution costs in the scenario of connection costs covered by the company owning
                                              and operating the DH network

               Considering that a feasibility condition for a DH pipe/trench is usually indicated as a minimum
               1.5-1.8  MWh/m linear  heat  density  (corresponding  to  distribution  costs  not  higher  than  8-10
               €/GJ, as evident in Figures 11 and 12), we may easily observe that: